On 31 October 2025, the Government of Tanzania published the Electricity (Development of Small Power Projects) (Amendment) Rules, GN No. 640 of 2025 (the “SPP Amendments”). These amendments fundamentally revise the 2020 SPP framework (G.N No. 491 of 2020), ushering in a new era of regulatory transparency, grid stability, and strategic renewable energy integration.
These changes are not merely administrative; they represent a strategic realignment of Tanzania’s energy market, prioritising dispatchable renewable capacity, eliminating contractual ambiguity, and introducing binding performance benchmarks. For the C-suite, board members, and project financiers, understanding these granular shifts is essential for compliance, bankability, and successful project execution.
Executive Summary: Key Changes at a Glance
| Aspect | Previous Position (2020 Rules) | New Position (2025 Amendments) | Impact on Investors |
| Project Size (SPP) | 100 kW – 10 MW (with potential for >10 MW under export restrictions) | Strictly 100 kW – 10 MW; no exceptions for larger capacities | Clearer eligibility; projects >10 MW must seek alternative licensing paths |
| Hybrid Systems | No explicit fossil fuel limitation | Fossil fuel generation capped at 25% of total installed capacity | Forces genuine renewable focus; many hybrid designs require technical re-evaluation |
| Strategic Areas | DNOs identified areas for development | DNOs must publish list of strategic areas annually in July in widely circulated newspapers; projects must offer additional commercial/technical benefits to DNO, approved by EWURA | Site selection becomes calendar-driven; early engagement with DNOs is critical |
| Standardised PPA (SPPA) | SPPA form prescribed in Third Schedule | Parties must sign EWURA-approved SPPA without substantive amendments; EWURA may issue standardised addenda for emerging technologies | Faster financial close; predictable contractual environment; flexibility for innovation |
| Performance Agreement | Not required | Mandatory Performance Agreement with EWURA, alongside license and SPPA | Licenses cannot be “parked”; binding milestones increase accountability |
| Dispute Resolution | Right to “appeal” DNO decisions to EWURA | Right to “refer the matter” to EWURA for determination | Streamlined regulatory resolution process |
| Avoided Cost | Broad description | Incremental cost savings realised by DNO when purchasing from another generator instead of self-generation | Clearer economic justification for SPP integration |
By the Numbers: Tanzania’s Renewable Energy Landscape
These regulatory changes are occurring against a backdrop of significant sector growth:
- Current grid-connected generation capacity: 2,138 MW (as of March 2024), a 14.2% increase from the previous year
- Private sector SPP contracts: 20 SPPs contracted to add 86.31 MW of decentralised renewable capacity
- National generation target Electricity generation to increase by 2,463 MW, with 58% from hydro, 35% from gas, and 7% from other renewables
- Grid Imara project: 4.2 trillion TZS allocated for nationwide substation construction
- Rural Energy Agency (REA) subsidy: 10 billion TZS for small renewable developers (mini-grids)
- Off-grid solar systems: 7,000 systems funded in rural areas
Part 1: Revised Definitions and Scope (Rule 3)
The 2025 amendments introduce sharper eligibility criteria that directly impact project qualification.
a) The 25% Hybrid Cap
Perhaps the most significant operational change is the introduction of a 25% fossil fuel generation cap for hybrid systems. Any project combining renewable sources with fossil fuels must ensure that electricity generated from fossil fuels does not exceed 25% of total installed capacity. This provision enforces a “green first” mandate, preventing developers from using hybrid designations to circumvent renewable energy policy objectives.
Investor Impact: Hybrid project designs must be revisited. Remote or islanded applications where 24/7 renewable reliability is challenging may require additional battery storage or over-sizing of renewable capacity to comply.
b) Unitisation of “Renewable Energy Sources”
The amendments update the definition of “renewable energy” to “renewable energy sources,” reflecting technological advancements and aligning with international terminology.
c) Strict Capacity Thresholds
The definition of an SPP Developer is now strictly tied to an installed capacity of between 100 kW and 10 MW. Critically, the previous provision allowing for projects above 10 MW to qualify as SPPs (under specific export limitations) has been deleted.
Investor Impact: Projects with installed capacity exceeding 10 MW must now pursue separate licensing frameworks, potentially under the broader Independent Power Producer (IPP) regime. Developers should assess whether project scaling is justified or if a sub-10 MW configuration is more advantageous under the SPP framework.
d) Avoided Cost Realignment
“Avoided Cost” is now explicitly defined as the incremental cost savings realised by a Distribution Network Operator (DNO) when purchasing electricity from another generator instead of generating it itself. This sharpens the economic justification required for SPP integration and provides a clearer methodology for tariff calculations.
Investor Impact: This definition clarifies how avoided cost is calculated, reducing disputes over tariff methodologies and providing greater certainty for project financial models.
e) Eligible Customer Expansion
The definition of “Eligible Customer” has been expanded. Under the new rules, an eligible customer may contract directly with a person licensed to generate electricity, replacing the earlier requirement that the contract be with a person licensed to supply electricity.
Investor Impact: This change opens new revenue streams for SPP developers, allowing direct sales to eligible customers (large industrial or commercial consumers) without intermediation by a DNO.
Part 2: Strategic Areas – Centralised Planning (Rule 4)
One of the most impactful changes for project site selection is the shift from opportunity-driven to centrally planned development.
Enhanced DNO Obligations
Distribution Network Operators (DNOs) are now mandated to identify and submit a list of “Strategic Areas” for SPP development to EWURA. Critically, DNOs must publish this list in widely circulated newspapers in Tanzania during the month of July annually. This ensures transparency for private developers.
Additional Commercial/Tech Benefit Requirement
Under the new subrule 2(c), proposed projects must offer additional commercial or technical benefits to the DNO, subject to DNO determination and approval by EWURA.
No Exceptions for VSPPs
Previously, subrule 8 exempted VSPP (Very Small Power Producer) projects already under construction from compliance with Rule 4. This subrule has been deleted. Consequently, all VSPP projects are required to comply with Rule 4 without exception, irrespective of their development stage.
Strategic Area Restriction
Amended subrule 3 restricts SPP developers to only developing projects in areas officially declared as strategic.
Investor Takeaway: Site selection is now data‑driven and calendar‑sensitive. Developers cannot proceed in an area unless it has been declared strategic and the project demonstrates clear “technical and commercial benefit” to the DNO, as approved by EWURA. Align your project pipeline with the July publications and engage DNOs early.
Part 3: Licensing and Dispute Resolution (Rules 7 & 11)
The amendments modernise cross‑references to other prevailing laws, eliminating procedural ambiguity.
Updated Licensing Framework
Rule 7 now explicitly refers to the Electricity (Generation, Transmission and Distribution Activities) Rules (without restrictive reference to the 2019 version), ensuring that SPP developers follow the most current and robust licensing protocols.
Streamlined Dispute Resolution
Rule 7 dispute resolution has been amended: the terminology has shifted from “appealing” a DNO’s decision to “referring the matter to the Authority for determination.” This suggests a more streamlined regulatory resolution process, reducing the adversarial nature of disputes and potentially accelerating outcomes.
Investor Takeaway: Use the current licensing rules as your procedural reference. The dispute resolution mechanism is now more collaborative, but developers should ensure their contracts reflect the new “referral” pathway.
VSPP Endorsement Requirement (Rule 5)
A new requirement has been added for VSPP applications: Mini‑grid developers must now obtain an endorsement from the Rural Energy Agency (REA) before submitting their applications to EWURA.
Investor Takeaway: For mini‑grid projects, factor in an additional step for REA endorsement before proceeding to EWURA. This reinforces the role of REA in rural electrification planning.
Quarterly Reporting Removed (Rule 6)
Rule 6, which previously required VSPP developers to submit quarterly progress reports to EWURA and the Ministry (with automatic expiration of letters of support for non‑compliance), has been deleted.
Investor Takeaway: Reduced administrative burden for VSPP developers, though broader compliance obligations remain.
Part 4: Standardised Power Purchase Agreements – Contractual Certainty (Rule 35)
To eliminate “negotiation fatigue” that has historically delayed energy projects, Rule 35 has been strengthened.
Inviolability of the SPPA
Under revised Rule 35(1), any PPA entered into between a DNO and a seller for the sale of electricity must be executed in the SPPA form as prescribed by EWURA, replacing the previous reference to the Third Schedule. New subrules (7), (8), and (9) require that:
- A SPP developer and a DNO sign the EWURA‑approved SPPA without substantive amendments
- This creates a predictable contractual environment, welcomed by international financiers and development finance institutions.
Power of Addenda
EWURA is empowered to issue standardised addenda to address emerging technologies or project‑specific innovations (e.g., advanced battery storage, peer‑to‑peer energy sharing, green hydrogen integration), specifying technical and operational requirements.
Existing SPPAs
Parties to existing SPPAs are mandated to adopt such addenda where required, ensuring consistency, adaptability, and alignment with evolving industry standards.
Investor Takeaway: Expect faster closing times. Your legal leverage shifts from rewriting terms to negotiating addenda. This standardisation is a major de‑risking factor for project financiers.
Part 5: Performance Monitoring and Accountability (Rules 36 & 58)
The 2025 Rules place a premium on delivery, not just approvals.
Performance Agreement Requirement
Rule 58 has been amended to add a new subrule (3), introducing an additional compliance obligation: every SPP developer must sign a Performance Agreement with EWURA, alongside the existing requirement to submit annual reports.
Investor Takeaway: This Performance Agreement acts as a binding benchmark for project milestones, ensuring that licences are not “parked” but are actively moved toward commissioning. Factor milestone compliance into your project management from day one.
Updated Licensing Reference
Rule 36 has been amended by removing the restrictive reference to the year “2019.” The provision now requires SPP developers to apply for a licence in accordance with the Electricity (Generation, Transmission and Distribution Activities) Rules (current version).
Part 6: VSPP Framework Changes
Very Small Power Producers (VSPPs) are not exempt from the revised framework.
- Rule 5 (VSPP Criteria) Now requires REA endorsement before EWURA submission
- Rule 6 (Quarterly Reports) Deleted – reduced administrative burden
- Rule 4 (Strategic Areas) Exemption for VSPPs under construction deleted – now fully applicable
Part 7: Technical and Interconnection Requirements
Grid Interconnection Guidelines
All SPPs connected to the distribution network in Tanzania are considered Embedded Generators. The Guidelines For Grid Interconnection of Small Power Projects establish procedures and equipment to protect personnel, equipment, and DNO systems from harmful effects arising out of interconnection and operation of Embedded Generators.
Provisional Registration
EWURA may provide a provisional registration for an SPP or VSPP that fulfils the registration requirements at any stage before commissioning of the project by way of a letter. Additionally, EWURA may issue a provisional licence to allow a developer to conduct preparatory activities, such as carrying out assessments, studies, and other activities necessary for the licence application.
Strategic Implications for International Investors
Site Selection
Project site selection must be strictly data‑driven based on the DNO’s July strategic area publications. Early engagement with DNOs and EWURA is essential.
Financial Modelling
The 25% fossil fuel cap on hybrids requires a re‑evaluation of technical designs for projects in remote areas where 24/7 renewable reliability may be a challenge. Factor in energy storage costs or over‑sizing of renewable capacity.
Contractual Certainty
The non‑negotiable SPPA reduces negotiation costs and timelines, but developers must ensure their technical specifications align with EWURA‑approved addenda.
Performance Compliance
The mandatory Performance Agreement introduces binding milestones. Develop internal project management systems to track and report progress against these benchmarks.
Currency and Tariffs
SPPs receive fixed tariffs calculated annually, with technology‑specific feed‑in tariffs for small hydro and biomass projects, and competitive bidding to establish tariffs for solar and wind projects. Payments are in US dollars or another hard currency.
Step‑by‑Step Compliance Roadmap for Developers
| Step | Action | Timing | Key Reference |
| 1 | Identify strategic areas from DNO’s July publication | Annually (July) | Rule 4(6) |
| 2 | Demonstrate technical/commercial benefit to DNO | Before site selection | Rule 4(2)(c) |
| 3 | Obtain DNO determination and EWURA approval | Varies | Rule 4(2)(c) |
| 4 | Execute EWURA‑approved SPPA without amendments | After DNO/EWURA approvals | Rule 35(7) |
| 5 | Apply for licence under current Generation Rules | After SPPA execution | Rule 36 |
| 6 | Sign Performance Agreement with EWURA | Concurrent with licensing | Rule 58(3) |
| 7 | Obtain provisional registration/provisional licence (if applicable) | Before commissioning | EWURA practice |
| 8 | Commission project and obtain final registration certificate | After commissioning | EWURA practice |
Frequently Asked Questions
Q1: Can I still develop an SPP with installed capacity above 10 MW?
No. The previous allowance for projects above 10 MW with export restrictions has been deleted. Projects exceeding 10 MW must pursue alternative licensing frameworks.
Q2: How is “avoided cost” calculated under the new rules?
Avoided cost means the incremental cost savings realised by a DNO when purchasing electricity from another generator instead of generating it itself. This clarifies the economic justification required for SPP integration.
Q3: What happens if my project area is not declared “strategic”?
You cannot proceed in that area. Developers are restricted to officially declared strategic areas only.
Q4: Can I negotiate the standardised SPPA?
No. Parties must execute the EWURA‑approved SPPA without substantive amendments. However, EWURA may issue standardised addenda to accommodate project‑specific innovations.
Q5: What is the Performance Agreement, and what happens if I miss milestones?
The Performance Agreement is a binding agreement with EWURA setting out project milestones. While the specific consequences of missed milestones are determined on a case‑by‑case basis, the agreement ensures licences cannot be “parked” without progress.
Q6: Are mini‑grids (VSPPs) exempt from any requirements?
No. The previous exemption for VSPPs under construction has been deleted. All VSPP projects must now comply with Rule 4 (Strategic Areas) and obtain REA endorsement before EWURA submission.
Q7: Can I sell electricity directly to customers?
Yes. Under the amended definition of “Eligible Customer,” you may contract directly with a person licensed to generate electricity, replacing the earlier requirement for a supply licence.
Q8: What currency are SPP payments made in?
Payments are in US dollars or another hard currency, providing currency stability for international investors.
Looking Ahead: What’s Next for Tanzania’s SPP Framework?
The 2025 SPP Amendments are part of a broader policy shift. In the coming years, developers should anticipate:
- Further standardisation of tariff methodologies for solar and wind projects through competitive bidding
- Expansion of the “Strong Grid” (Grid Imara) project – substations in every district nationwide at an estimated total cost of 4.2 trillion TZS, improving grid stability and enabling greater SPP integration
- Operationalisation of the Renewable Energy Investment Facility (REIF) – scaling up local private sector investment in rural renewable energy through matching grants, results‑based financing, credit lines, and risk mitigation instruments
- Potential introduction of peer‑to‑peer energy sharing frameworks – EWURA has been encouraged to remain receptive to such innovations
How Rive & Co Can Support Your SPP Project
At Rive & Co, we specialise in guiding international developers and investors through Tanzania’s evolving energy regulatory landscape. Our services include:
- Strategic Area confirmations – engaging DNOs and EWURA to validate site eligibility and demonstrate technical/commercial benefits
- Hybrid system compliance reviews – ensuring your generation mix respects the 25% fossil fuel cap
- SPPA execution and addenda negotiation – protecting your interests while respecting the standardised form
- Performance Agreement drafting and milestone tracking – keeping your project compliant from licence to commissioning
- Licensing and registration support – navigating provisional registration, provisional licences, and final commissioning requirements
Author: Sunday Ndamugoba (Sunday@rive.co.tz)
Legal & Investment Disclaimer
This guide is provided for general informational purposes only and does not constitute legal, financial, or investment advice. While every effort has been made to ensure the accuracy of the information provided, the legal and regulatory landscape is subject to change. Readers should not act upon the information contained in this guide without obtaining specific legal, financial, and technical counsel regarding their particular circumstances and jurisdiction. Past performance does not guarantee future results. This guide does not constitute an offer to sell or a solicitation of an offer to buy any securities or investment products.