A force majeure notice is a claim, and nothing more at this stage. The party that sent it wants to be excused from an obligation, or to have time to perform it, and it is asking you to accept that. What you do in the first days after it arrives decides how many of your rights you keep.
Notices are arriving more often. Export controls, port delays, regulatory suspensions, power failures and supplier defaults are all being pleaded as force majeure, and the pressure on supply chains for metals and battery materials is adding to the number. This guide is written for the business that receives the notice. It covers Mainland Tanzania, and Zanzibar contracts should be read against the Contract Decree, Cap. 149 of the Laws of Zanzibar.
Start with the right question
Many recipients ask whether the event is really force majeure. That is the second question. The first is whether your contract gives the sender any right to rely on it at all.
In Tanzania force majeure works through the contract. If your agreement has no force majeure clause, the sender cannot invoke one, because the clause is not implied by law. The sender is then left with the statutory rule on supervening impossibility in section 56(2) of the Law of Contract Act, Cap. 345, which is much narrower. It provides that a contract to do an act which, after the contract is made, becomes impossible, or becomes unlawful by reason of an event the promisor could not prevent, becomes void when the act becomes impossible or unlawful. Higher cost, lost profit and commercial inconvenience do not meet that test.
The first 48 hours
Speed matters, and so does restraint. These steps protect your position before you have decided what to do.
- Diarise every date in the notice and in the clause, including any time limit for your response and any period after which a termination right arises.
- Acknowledge receipt in writing, state that you are reviewing the notice, and reserve all rights. Do not agree, and do not reject, until you have read the clause.
- Keep performing what you can. Pay what is due, deliver what you can deliver and keep supplying your side of the contract, so that nobody can say you waived your rights or repudiated.
- Do not terminate at once. A termination that the contract does not allow can be a breach by you.
- Preserve documents. Collect the contract, its amendments, earlier notices, correspondence about the event and your own records of orders, shipments and payments.
Read the clause against the notice
Most disputes are won or lost on seven points.
- Does the event fall within the clause? Clauses either list events, use a general test such as circumstances beyond reasonable control, or do both. A listed clause is read as written. A general phrase after a list is usually read in light of the list.
- Was the notice given as the clause requires? Check the deadline, the form, the addressee and the content. Where the clause makes notice a condition of relief, a late or defective notice can defeat the claim.
- Did the event cause the failure to perform? The sender must show that the event, and not its own decisions, stock position or finances, prevented performance. A party that would have failed anyway cannot blame the event.
- Which obligations does it excuse? Many clauses excuse delivery or performance but leave payment obligations in place. Others suspend minimum volume, take or pay and exclusivity obligations. Read the exact words.
- Does the clause require mitigation? Most do, expressly or by implication. The sender should show that it looked for alternative supply, alternative routes or alternative methods.
- What is the effect, suspension or release? Some clauses suspend obligations for the duration of the event. Others extend time or allow either party to terminate once the event has lasted a fixed period.
- When can you terminate? Look for a long stop date, often 60, 90 or 180 days, after which the unaffected party can walk away.
Test the claim and make the sender prove it
The party that relies on a force majeure clause carries the burden of proving that it applies. Section 110 of the Evidence Act, Cap. 6, places the burden on the person who asks the court to give judgment on facts they assert, and section 115 shifts the burden to a party where a fact is especially within its knowledge. The sender’s internal records, supplier correspondence and operational data are matters within its knowledge, so you are entitled to ask for them.
Write to the sender and ask, within a short and specific period, for the following.
- The documents that show the event, such as the government order, the port or carrier notice, the supplier’s letter or the incident report.
- A statement of exactly which obligations are affected, from what date, and for how long the sender expects the effect to last.
- Evidence that the event caused the failure to perform, including the sender’s position before the event.
- The steps taken to mitigate, including alternative sources, routes and methods, and the cost of each.
- Confirmation of how the sender is treating its other customers, because a party that keeps performing for other buyers while excusing itself from you will have to explain why.
Silence or vague answers are useful to you. They go to causation and mitigation, and they are what a court or tribunal will look at first.
Check your own exposure
A notice often triggers a chain. If you resell, process or deliver what the sender was due to supply, you may be about to miss obligations of your own. Look at your downstream contracts at once. Check whether their force majeure clauses cover a failure by your supplier, give notice under them in time, and mitigate your own loss by sourcing from elsewhere where that is reasonable. Keep records of the extra cost of cover, because it is the starting point of any damages claim against the sender if the clause fails.
The law also expects the innocent party to mitigate. If the sender is in breach and you have a right to damages, you must take reasonable steps to limit your loss, and the cost of reasonable substitute supply is usually recoverable.
Frustration is a separate and narrower route
If the sender relies on the general law and not a clause, the question is whether performance has become impossible or unlawful under section 56(2). The event must occur after the contract is made, it must be beyond the sender’s control, and it must make performance impossible or unlawful, not merely harder or more expensive. If it applies, the contract becomes void from that point, and the Law of Contract Act requires a person who has received an advantage under a contract that has become void to restore it or pay compensation for it. Money paid in advance, goods delivered and work done will therefore need to be accounted for.
Courts do not lightly find frustration. A change in price, a shortage that can be met from another source or a delay that can be absorbed will not do. If the sender cannot show that its position is truly impossible, the notice is a breach in a different dress.
Your options
Accept and agree terms
Where the claim is sound, accept it in writing on stated terms: the period of suspension, a revised delivery schedule, what happens to payments already made, who bears storage and demurrage, and a date on which the position will be reviewed. A short written variation protects both sides.
Reject with reasons
Where the claim fails on the clause, the notice or the facts, reject it in a reasoned letter that points to the wording, states what you will continue to do, and reserves your right to damages and to terminate. A reasoned rejection is far stronger than a bare denial.
Renegotiate
Many notices are an opening position for a renegotiation of price, volume or timing. A partial performance arrangement, a staged delivery plan or a price adjustment can preserve a relationship that a dispute would destroy. Record any agreement in a signed variation and state that it is not a waiver of other rights.
Terminate or escalate
If the long stop date has passed or the clause allows termination, give the termination notice in the form and within the time the contract requires. If there is a dispute, follow the contract’s escalation steps, then arbitration or court proceedings under its dispute clause. The Arbitration Act, Cap. 15 R.E. 2023, governs arbitrations seated in Mainland Tanzania. Natural resources agreements with Cabinet approval may provide a different seat under section 11(4) of the Natural Wealth and Resources (Permanent Sovereignty) Act, Cap. 449.
What your reply should contain
- A statement that you have received the notice and the date you received it.
- A reference to the clause and the point in it that you accept or contest.
- A reservation of all your rights, including damages and termination.
- A list of the documents and information you require and the date by which you need them.
- A statement of what you will continue to perform and what you expect the sender to continue to perform.
- An invitation to meet and discuss mitigation and a workable schedule.
Frequently asked questions
Does a force majeure notice excuse the sender from paying me?
Not automatically. Many clauses cover delivery and performance but leave payment obligations in place. Read the wording.
Can I terminate as soon as I receive the notice?
Only if the contract gives you that right. Terminating early without a contractual basis can make you the party in breach.
My contract has no force majeure clause. Can the sender still rely on it?
No clause can be implied. The sender is left with section 56(2) of the Law of Contract Act, which requires true impossibility or illegality after the contract was made.
Is a price rise or a shortage force majeure?
Usually not. A clause that does not list cost increases or market movements will rarely be read to cover them, and frustration does not apply to commercial hardship.
What if the sender gave notice late?
It depends on the clause. Where notice is expressed as a condition of relief, late notice can lose the sender its protection. Where it is not, the effect of the delay depends on the wording and on any prejudice it caused you.
Who has to prove the event?
The sender. Under section 110 of the Evidence Act, the party who asserts the facts that bring it within the clause must prove them.
Does a government order count?
If your clause lists acts of government, regulatory action or change in law, it can. If it does not, the sender will need the general words to reach it, and the sender must still show the order made performance impossible or prevented it.
Before you reply
If you have received a force majeure notice, send it to me together with the contract and any related correspondence. I can read the clause, assess the claim and prepare your reply before your response time runs out. Write to sunday@rive.co.tz.
Legislation
- Law of Contract Act, Cap. 345, section 56.
- Evidence Act, Cap. 6, sections 110 to 112 and 115.
- Arbitration Act, Cap. 15 R.E. 2023.
- Natural Wealth and Resources (Permanent Sovereignty) Act, Cap. 449, section 11(4), inserted by Act No. 7 of 2026.
- Contract Decree, Cap. 149 of the Laws of Zanzibar.
About the author
Sunday Ndamugoba is a Partner at RIVE & Co and leads the Corporate department. He is an Advocate of the High Courts of Tanzania and Zanzibar, a registered arbitrator and an accredited mediator, and the author of Doing Business in Tanzania and Zanzibar. Email: sunday@rive.co.tz
Disclaimer
This article is general information and does not constitute legal advice. The law is stated as at 2 November 2026 and may change. The outcome of any force majeure claim depends on the wording of the contract and the facts. Do not act on this article without advice on your specific facts from a qualified advocate. RIVE & Co and the author accept no liability for loss arising from reliance on it.
SEO details
Suggested title tag: Received a force majeure notice in Tanzania? What to do next.
Suggested meta description: A practical guide for Tanzanian businesses that receive a force majeure notice: how to read the clause, test the claim, protect your rights and respond.
Keywords: force majeure Tanzania, force majeure notice, frustration of contract Tanzania, section 56 Law of Contract Act, Tanzania contract law, force majeure clause, breach of contract Tanzania, Tanzania commercial disputes, contract termination Tanzania, supply contract dispute.